Headroom - Project Charter & Specifications

Version: 1.0
Date: February 17, 2026
Status: Approved for Development


Executive Summary

Headroom is a resource planning and capacity management tool designed to solve the allocation chaos faced by engineering managers juggling multiple projects and team members. It replaces error-prone spreadsheets with a structured system that tracks capacity, forecasts utilization, prevents over/under-billing, and provides clear visibility into team allocation.

Target Users:

  • Engineering managers (10-15 person teams)
  • Managing 10-12 concurrent projects in various stages
  • Need month-by-month capacity planning and allocation tracking

Core Value Proposition:

  • Know exactly who has headroom for new work
  • Prevent billing errors (over-allocation → overcharge, under-allocation → undercharge)
  • Forecast revenue based on approved estimates and current allocations
  • Track planned vs actual hours to understand team utilization

Problem Statement

Current Pain Points

The Spreadsheet Nightmare:

  • Manual capacity calculations across holidays, PTO, weekends
  • No validation (easy to over-allocate people or projects)
  • Hard to see at a glance: "Who has capacity this month?"
  • Billing forecasts require manual formula updates
  • No audit trail of allocation changes
  • Difficult to track planned vs actual hours

Business Impact:

  • Over-allocation: Leads to overcharging clients → escalations, unhappy customers
  • Under-allocation: Leads to undercharging → revenue loss, unhappy management
  • Resource conflicts: Multiple managers allocating the same person without visibility
  • Forecast inaccuracy: Can't reliably predict revenue or capacity needs

Solution Overview

Headroom provides a structured workflow for capacity planning and resource allocation:

┌─────────────────────────────────────────────────────────────────┐
│              MONTHLY CAPACITY PLANNING CYCLE                    │
├─────────────────────────────────────────────────────────────────┤
│                                                                  │
│    STEP 1: CAPACITY PLANNING                                    │
│    ────────────────────────────────────────────────────         │
│    • Define team members (name, role, hourly rate)             │
│    • Mark holidays, PTO, weekends for the month                │
│    • Set availability per day (1=full, 0.5=half, 0=unavailable)│
│                                                                  │
│    OUTPUT:                                                       │
│    • Individual capacity (person-days per month)                │
│    • Team capacity (total available person-days)                │
│    • Possible revenue (capacity × hourly rates)                 │
│                                                                  │
├─────────────────────────────────────────────────────────────────┤
│    STEP 2: PROJECT SETUP                                        │
│    ────────────────────────────────────────────────────         │
│    • Track project status (Initial → Estimates → Funded → ...)  │
│    • Define approved estimate (total billable hours)            │
│    • Forecast effort distribution across months                │
│                                                                  │
│    OUTPUT:                                                       │
│    • Month-wise project forecast                                │
│    • Alerts when forecast ≠ approved estimate                   │
│                                                                  │
├─────────────────────────────────────────────────────────────────┤
│    STEP 3: RESOURCE ALLOCATION                                  │
│    ────────────────────────────────────────────────────────────│
│    • Allocate hours per person per project per month           │
│    • Validation: total allocation ≤ team capacity              │
│    • Validation: project allocation = approved estimate        │
│    • "Untracked" bucket for external team time                 │
│                                                                  │
│    OUTPUT:                                                       │
│    • Clear view: who's allocated to what                        │
│    • Over/under allocation indicators (RED flags)               │
│    • Running utilization % per person                           │
│                                                                  │
├─────────────────────────────────────────────────────────────────┤
│    STEP 4: ACTUALS TRACKING                                     │
│    ────────────────────────────────────────────────────────────│
│    • Team members log hours worked (monthly aggregate)         │
│    • Manual entry (no time-tracking tool integration for MVP)  │
│                                                                  │
│    OUTPUT:                                                       │
│    • Running utilization (allocated vs capacity YTD)            │
│    • Overall utilization (allocated % per month)                │
│    • Variance: planned vs actual                                │
│                                                                  │
└─────────────────────────────────────────────────────────────────┘

Complete Requirements

1. Capacity Planning

Inputs:

  • Team member list (name, role/team, hourly rate)
  • Calendar data per month (holidays, weekends)
  • Individual PTO requests
  • Daily availability (1.0 = full day, 0.5 = half day, 0 = unavailable)

Calculations:

  • Individual capacity = Σ(working days × availability)
  • Team capacity = Σ(individual capacities)
  • Possible revenue = Σ(individual capacity × hourly rate)

Outputs:

  • Individual capacity report (person-days per month)
  • Team capacity summary
  • Revenue potential (if fully utilized)

Validation Rules:

  • Availability must be 0, 0.5, or 1.0
  • Hourly rate must be > 0
  • Working days must exclude holidays, weekends, PTO

2. Project Management

Project Attributes:

  • Project ID (unique identifier)
  • Project title
  • Type: Project (billable) / Support (ongoing ops)
  • Status (see state machine below)
  • Approved estimate (total billable hours)
  • Forecasted effort (month-by-month breakdown)

Project Status State Machine:

NA/Support → Initial → Gathering Estimates → Estimate Pending Approval
                ↓
        Estimate Rework ←───────┘
                ↓
        Estimate Approved → Funded → Scheduled → In-Progress
                ↓
        Ready for Prod → Done
                ↓
        [Optional: On-Hold, Cancelled]

Outputs:

  • Month-wise forecast per project
  • Alert when Σ(forecasted effort) ≠ approved estimate (RED flag)
  • Alert when monthly team allocation > team capacity (RED flag)

Validation Rules:

  • Approved estimate must be > 0
  • Forecasted effort sum must equal approved estimate (±tolerance)
  • Cannot allocate hours to projects in status "Done" or "Cancelled"

3. Resource Allocation

Allocation Matrix:

For selected month M:
┌────────────────────────────────────────────────────┐
│ Project    │ Dev A │ Dev B │ Dev C │ Untracked │  │
├────────────┼───────┼───────┼───────┼───────────┼──┤
│ Project X  │  40h  │  20h  │   0   │    10h    │  │
│ Project Y  │  20h  │  40h  │  30h  │     0     │  │
│ Project Z  │   0   │  80h  │  60h  │     0     │  │
├────────────┼───────┼───────┼───────┼───────────┼──┤
│ Total      │  60h  │ 140h  │  90h  │    10h    │  │
│ Capacity   │ 160h  │ 160h  │ 120h  │     ∞     │  │
│ % Util     │  38%  │  88%  │  75%  │    N/A    │  │
└────────────────────────────────────────────────────┘

Features:

  • Allocate hours per person per project per month
  • "Untracked" resource for external team time (no billing tracked)
  • Visual indicators:
    • GREEN: Allocation = Approved estimate (100%)
    • YELLOW: Under-allocated (< 100%)
    • RED: Over-allocated (> 100%)

Outputs:

  • Allocation summary per month
  • Per-project allocation % (allocated / approved estimate)
  • Per-person utilization % (allocated / capacity)
  • Over/under allocation flags

Validation Rules:

  • Cannot allocate negative hours
  • Cannot allocate more than person's monthly capacity (warning, not hard block)
  • Cannot allocate to non-existent project or person
  • Sum of project allocations should equal approved estimate (tolerance: ±5%)

4. Actuals & Utilization Tracking

Data Entry:

  • Team members log hours worked per project per month
  • Entry method: Manual (monthly aggregate)
  • Updates: Can be incremental (weekly updates accumulate)

Calculations:

  • Running utilization: (Allocated hours YTD) / (Capacity YTD) × 100%
  • Overall utilization: (Allocated hours this month) / (Capacity this month) × 100%
  • Variance: Actual hours - Allocated hours (per project, per person)

Outputs:

  • Actuals vs Planned comparison
  • Utilization metrics (running, overall)
  • Variance reports (where did we over/under-deliver?)

Validation Rules:

  • Cannot log negative hours
  • Cannot log hours for future months
  • Cannot log hours after project status = "Done" (configurable)

5. Reports & Analytics

Core Reports:

Report Description Filters
Forecast Summary Multi-period forecast of allocations and revenue Date range, team, project, status
Utilization Summary Team and individual utilization trends Date range, team member, role
Cost Summary Revenue forecasts based on allocations × hourly rates Date range, project, client
Allocation Report Who's allocated to what, month-by-month Month, team, project
Variance Report Planned vs Actual analysis Date range, project, person

Report Features:

  • Highly customizable filters (team, person, project, status, date range, type)
  • Export capabilities: Defer to Phase 2 (PDF/CSV)
  • Caching: Redis caching for expensive queries

6. Role-Based Access Control (RBAC)

Personas & Permissions:

Persona Access Rights Restrictions
Superuser Full access: setup, config, all projects, all teams None
Manager • Create/edit projects
• Allocate resources to own team
• View all projects (read-only for other teams)
• Approve estimates
• View team's utilization reports
• Cannot allocate other teams' members
• Cannot edit other managers' projects
Developer • View own allocations
• Log own hours (actuals)
• View project details for assigned projects
• Cannot allocate resources
• Cannot change estimates
• Cannot view other developers' allocations
Top Brass • View all reports (read-only)
• Forecast summaries
• Utilization dashboards
• Cost summaries
• Cannot modify anything
• Read-only access only

Access Control Implementation:

  • Laravel Policies for model-level authorization
  • Middleware for route-level guards
  • JWT tokens with role claims

Data Validation Rules

These rules drive API validation, tests, and verification:

Team Members

  • Name: Required, max 255 chars
  • Role/Team: Required, must exist in master data
  • Hourly rate: Required, > 0, numeric (2 decimal places)
  • Availability: Must be 0, 0.5, or 1.0

Projects

  • Project ID: Unique, required
  • Title: Required, max 255 chars
  • Type: Must be "Project" or "Support"
  • Status: Must be valid state (see state machine)
  • Approved estimate: Required if status ≥ "Estimate Approved", > 0
  • Forecasted effort: Sum must equal approved estimate (±5% tolerance)

Allocations

  • Person ID: Must exist in team members
  • Project ID: Must exist in projects
  • Hours: >= 0, numeric (2 decimal places)
  • Month: Valid date (YYYY-MM format)
  • Sum of allocations per project ≤ approved estimate + 5%
  • Sum of allocations per person ≤ capacity + 20% (warning threshold)

Actuals

  • Person ID: Must exist in team members
  • Project ID: Must exist in projects
  • Hours: >= 0, numeric (2 decimal places)
  • Month: Must be current or past month (cannot log future hours)
  • Cannot log hours if project status = "Cancelled" or "Done" (configurable)

Holidays/PTO

  • Date: Valid date
  • Type: "Holiday" or "PTO"
  • If PTO: must be associated with a team member

Technical Stack

Backend (Laravel API)

Component Technology Rationale
Framework Laravel 12 (latest) Robust PHP framework, rich ecosystem
Database PostgreSQL Production-grade, ACID compliant, great for reporting
Caching Redis Query + response caching from day 1
Authentication JWT (tymon/jwt-auth) Token-based, suitable for SPA frontend
API Design REST + Laravel API Resources Standard, well-understood, consistent JSON
API Docs Laravel Scribe (SwaggerUI) Auto-generated from code comments
Testing PHPUnit (unit) + Pest (feature) Laravel standard
Code Style PSR-12, Laravel conventions Industry standard
Containerization Docker (port 3000) Isolated, reproducible
Environment .env files Simple configuration management

Frontend (SvelteKit)

Component Technology Rationale
Framework SvelteKit Modern, reactive, great for dashboards
Styling Tailwind CSS + DaisyUI Fast development, consistent theming
Charts Recharts Good balance of power and simplicity
Tables TanStack Table (React Table) Industry standard, powerful filtering/sorting
Forms Superforms + Zod Type-safe validation, seamless SvelteKit integration
Form Actions SvelteKit native Server-side form handling
State Management Svelte stores (minimal) UI state only (filters, modals)
HTTP Client fetch (native) No extra dependencies
Testing Vitest (unit) + Playwright (E2E) Fast, modern testing tools
Containerization Docker (port 5173) Isolated, hot-reload for dev

Infrastructure & Deployment

Component Technology Rationale
Local Dev Docker Compose Code-mounted volumes, hot reload
Reverse Proxy Nginx Proxy Manager (existing) Already running in environment
Database Volume Mounted directory Portability, easy backup
Secrets .env files (all environments) Simple, consistent across envs
Background Jobs Laravel Queue + Redis (Phase 2) Deferred for MVP, easy to add

Quality Standards & Testing Strategy

Test Requirements (Per Change)

Every OpenSpec change must include:

  1. Unit tests (backend + frontend)
    • Coverage target: >70%
    • PHPUnit (Laravel), Vitest (SvelteKit)
  2. E2E tests (Playwright)
    • Happy path + critical error cases
  3. Regression tests
    • Run full test suite on each change

Code Review Checklist

Before merge, verify:

  • Style: PSR-12 (PHP), Prettier (JS), ESLint (SvelteKit)
  • Standards: Laravel conventions, SvelteKit best practices
  • Security: Input validation, SQL injection prevention, XSS protection, CSRF tokens
  • Tests: All tests passing, coverage >70%

Verification Workflow

/opsx-verify must check:

  • All tests passing
  • Code coverage >70%
  • No uncovered code (files without tests)
  • API docs up-to-date (Scribe generation)
  • No linting errors

Commit Standards

  • Granular commits: One fix = one commit
  • Commit message format:
    [Type] Brief description (50 chars max)
    
    Detailed explanation (optional, 72 char wrap)
    
    Refs: #issue-number (if applicable)
    
    Types: feat, fix, refactor, test, docs, chore

Issue-Driven Test Loop (Phase 2)

For E2E/integration failures:

  1. Test fails → Create GitHub issue
  2. Fix implementation
  3. Retest + regression test
  4. Close issue when all tests pass

For MVP: Run tests, fix inline (no issue creation yet).


Deferred Features (Phase 2+)

Deferred to Phase 2

Feature Rationale for Deferral Estimated Lift
Notifications (WebSocket) Allocations are monthly - not time-critical. Users can refresh. ~6 hours
PDF/CSV Exports On-screen reports sufficient for MVP. Easy to add later. ~4 hours
Background Jobs (async) No heavy processing in MVP. Laravel Queue ready when needed. ~2 hours
Audit Logging No compliance requirement for MVP. ~3 hours
Advanced Caching (pre-calculated reports) Start with on-demand queries. Cache if slow. ~4 hours
API Versioning (/api/v1/) Not needed until breaking changes. ~2 hours
Multi-language Support English-only for MVP. ~8 hours
Resource Over-allocation (advanced) MVP shows RED flag. Phase 2: predictive warnings, auto-balancing. ~6 hours

Explicitly Out of Scope

Feature Why Not Included
Time-tracking tool integration Manual entry sufficient. Integration adds vendor lock-in.
Mobile app Desktop web app is primary use case.
Invoicing integration Billing forecasts only. Actual invoicing is external.
Project task management Project-level tracking only, not task-level.
Calendar sync (Google, Outlook) Manual PTO/holiday entry is acceptable.
AI-powered forecasting Rule-based validation is sufficient for MVP.

Considerations & Trade-offs

Decision Log

Decision Option Chosen Alternative Considered Rationale
Multi-tenancy Single-tenant MVP, add tenant_id later Multi-tenant from day 1 Reduces complexity, easy to add later
Frontend framework SvelteKit Laravel + Vue, React Modern, reactive, great for dashboards
Authentication JWT Session-based Suitable for SPA, easier mobile support later
Caching Redis from day 1 Add later if needed Prevents refactoring technical debt
Notifications Defer to Phase 2 WebSocket PoC in MVP Not time-critical, saves 6 hours
Exports Defer to Phase 2 Include in MVP On-screen reports sufficient initially
Issue-driven tests Phase 2 From day 1 Slower velocity for MVP, add when more tests exist
API versioning Not included /api/v1/ from start No breaking changes expected in MVP

Known Limitations (MVP)

  1. No real-time updates: Users must refresh to see allocation changes
  2. Manual time entry: No automated time-tracking integration
  3. Single organization: No multi-tenancy support
  4. English only: No i18n support
  5. No mobile optimization: Desktop-first design

Success Metrics

MVP Success Criteria

Functional Completeness:

  • Users can define team capacity (members, holidays, PTO, availability)
  • Users can create projects with approved estimates
  • Users can allocate resources to projects month-by-month
  • Users can log actual hours worked
  • System validates allocations (over/under warnings)
  • Users can view 5 core reports (forecast, utilization, cost, allocation, variance)
  • RBAC enforced (4 personas: Superuser, Manager, Dev, Top Brass)

Quality Metrics:

  • All tests passing (unit + E2E)
  • Code coverage >70%
  • Zero linting errors
  • API documentation auto-generated (SwaggerUI)
  • Docker Compose setup working (local dev)

Usability Metrics (Post-Launch):

  • Manager can complete monthly allocation in <30 minutes (vs 2+ hours in spreadsheet)
  • Zero billing errors in first 3 months (over/under allocation caught before invoicing)
  • 90% of team members log actuals weekly (adoption metric)

Phase 2 Success Criteria

  • Real-time notifications working (WebSocket)
  • PDF/CSV exports available for all reports
  • Background jobs processing heavy reports
  • Audit logging capturing all changes

Timeline & Phases

MVP (Phase 1) - Core Functionality

Target: 6-8 weeks

Sprints:

  1. Project setup (1 week)

    • Docker Compose setup
    • Laravel + SvelteKit scaffolding
    • Database schema design
    • Authentication (JWT)
  2. Capacity planning (1.5 weeks)

    • Team member CRUD
    • Holiday/PTO calendar
    • Availability tracking
    • Capacity calculations
  3. Project management (1.5 weeks)

    • Project CRUD
    • Status state machine
    • Approved estimate tracking
    • Forecasted effort
  4. Resource allocation (2 weeks)

    • Allocation matrix UI
    • Validation rules
    • Over/under indicators
    • Untracked resource bucket
  5. Actuals & reporting (2 weeks)

    • Time logging interface
    • Utilization calculations
    • 5 core reports
    • Filters & customization
  6. Testing & polish (1 week)

    • E2E test coverage
    • Code review
    • Bug fixes
    • Documentation

Phase 2 - Enhancements

Target: 3-4 weeks (post-MVP)

  • Notifications (WebSocket)
  • Exports (PDF/CSV)
  • Background jobs
  • Audit logging
  • Advanced caching
  • Bug fixes from production use

Phase 3 - Scale & Optimize

Target: TBD (based on usage)

  • Multi-tenancy
  • Mobile optimization
  • AI-powered forecasting
  • Integration APIs (time-tracking, accounting)

Appendix: Master Data & Taxonomy

Configurable Lists (Admin-managed):

  1. Roles/Teams:

    • Frontend Developer
    • Backend Developer
    • QA Engineer
    • DevOps Engineer
    • UX Designer
    • Project Manager
    • Architect
  2. Project Statuses:

    • NA/Support
    • Initial
    • Gathering Estimates
    • Estimate Pending Approval
    • Estimate Rework
    • Estimate Approved
    • Funded
    • Scheduled
    • In-Progress
    • Ready for Prod
    • Done
    • On-Hold
    • Cancelled
  3. Project Types:

    • Project (billable)
    • Support (ongoing ops)
  4. Availability Options:

    • 0 (unavailable/PTO)
    • 0.5 (half day)
    • 1.0 (full day)
  5. Report Filters:

    • Date range (from/to)
    • Team member
    • Role/Team
    • Project
    • Project status
    • Project type

Document Control:

  • Owner: Santhosh J
  • Approver: Santhosh J
  • Next Review: Post-MVP completion
  • Change History:
    • v1.0 (2026-02-17): Initial charter approved

End of Project Charter