## ADDED Requirements
|
||
|
||
### Requirement: Generate cost summary report
|
||
The system SHALL generate reports showing revenue forecasts based on allocations multiplied by hourly rates.
|
||
|
||
#### Scenario: View monthly cost report
|
||
- **WHEN** viewing cost report for February 2026
|
||
- **THEN** the system displays all projects with their allocated hours
|
||
- **AND** calculates revenue for each project based on team member hourly rates
|
||
- **AND** shows total revenue forecast for the month
|
||
|
||
#### Scenario: Cost breakdown by project
|
||
- **WHEN** viewing cost report for a specific project
|
||
- **THEN** the system displays allocation breakdown by team member
|
||
- **AND** shows hours allocated and hourly rate for each team member
|
||
- **AND** calculates total project cost as sum of (hours × rate) for all team members
|
||
|
||
### Requirement: Filter cost report by project
|
||
The system SHALL allow filtering cost reports by project, client, or type.
|
||
|
||
#### Scenario: Filter by project type
|
||
- **WHEN** filtering cost report to show only "Project" type (billable)
|
||
- **THEN** the system displays revenue forecast for billable projects only
|
||
- **AND** excludes "Support" type projects
|
||
|
||
#### Scenario: Group by client
|
||
- **WHEN** grouping cost report by client
|
||
- **THEN** the system displays total revenue forecast per client
|
||
- **AND** shows breakdown of projects per client
|
||
|
||
### Requirement: Filter cost report by team
|
||
The system SHALL allow filtering cost reports by team or team member.
|
||
|
||
#### Scenario: Cost report for team member
|
||
- **WHEN** filtering cost report to show allocations for "John Doe"
|
||
- **THEN** the system displays all projects where John Doe is allocated
|
||
- **AND** calculates John's contribution to revenue (his hours × his rate)
|
||
|
||
#### Scenario: Cost report for role
|
||
- **WHEN** filtering by "Backend Developer" role
|
||
- **THEN** the system displays revenue generated by all Backend Developers
|
||
- **AND** shows average hourly rate for the role
|
||
|
||
### Requirement: Calculate total possible revenue
|
||
The system SHALL calculate maximum possible revenue if all team capacity were utilized at 100%.
|
||
|
||
#### Scenario: Possible revenue calculation
|
||
- **WHEN** viewing cost summary
|
||
- **THEN** the system calculates total team capacity (all team members' available hours)
|
||
- **AND** multiplies by each team member's hourly rate
|
||
- **AND** displays "Possible Revenue: $X if fully utilized"
|
||
|
||
### Requirement: Calculate forecasted revenue
|
||
The system SHALL calculate forecasted revenue based on current allocations.
|
||
|
||
#### Scenario: Forecasted revenue based on allocations
|
||
- **WHEN** team has 1000 hours total capacity
|
||
- **AND** currently 850 hours are allocated across projects
|
||
- **AND** the weighted average hourly rate is $140
|
||
- **THEN** the system calculates forecasted revenue as $119,000 (850 × $140)
|
||
|
||
### Requirement: Show revenue variance
|
||
The system SHALL display variance between possible revenue and forecasted revenue.
|
||
|
||
#### Scenario: Revenue gap analysis
|
||
- **WHEN** possible revenue is $150,000
|
||
- **AND** forecasted revenue is $119,000
|
||
- **THEN** the system displays revenue gap of $31,000 (20.7% underutilization)
|
||
|
||
### Requirement: Multi-period cost forecast
|
||
The system SHALL generate cost forecasts across multiple months.
|
||
|
||
#### Scenario: Quarter revenue forecast
|
||
- **WHEN** viewing cost report for Q1 2026 (Jan-Mar)
|
||
- **THEN** the system displays monthly revenue forecast for each month
|
||
- **AND** calculates total Q1 revenue forecast
|
||
- **AND** shows monthly variance from possible revenue
|
||
|
||
### Requirement: Export cost data
|
||
The system SHALL allow exporting cost report data (deferred to Phase 2 for PDF/CSV).
|
||
|
||
#### Scenario: View cost data on screen (MVP)
|
||
- **WHEN** viewing cost report
|
||
- **THEN** the system displays all cost data on screen in tabular format
|
||
- **AND** PDF/CSV export buttons are not available (Phase 2 feature)
|