## Context
|
||
|
||
Headroom is a greenfield web application to replace manual spreadsheet-based capacity planning for engineering teams. The current spreadsheet approach is error-prone, lacks validation, provides no audit trail, and wastes manager time (2+ hours monthly on allocation work).
|
||
|
||
**Current State:**
|
||
- No existing system to migrate from
|
||
- Team uses spreadsheets for capacity planning and resource allocation
|
||
- No automation, no validation, no visibility into team headroom
|
||
|
||
**Constraints:**
|
||
- MVP must be production-ready with >70% test coverage
|
||
- Must run containerized (Docker Compose) from day 1
|
||
- Existing Nginx Proxy Manager in environment (no Caddy/Traefik)
|
||
- Must support 10-15 developers across 10-12 concurrent projects
|
||
- Monthly capacity planning cycle (not real-time)
|
||
|
||
**Stakeholders:**
|
||
- Engineering managers (primary users)
|
||
- Team members (log hours, view allocations)
|
||
- Top brass (view reports only)
|
||
- Superuser/admin (system configuration)
|
||
|
||
---
|
||
|
||
## Goals / Non-Goals
|
||
|
||
**Goals:**
|
||
- Automate capacity calculations (holidays, PTO, availability)
|
||
- Validate allocations against capacity and approved estimates
|
||
- Prevent billing errors (over/under-allocation detection)
|
||
- Provide clear visibility into team headroom
|
||
- Track planned vs actual hours for utilization analysis
|
||
- Generate 5 core reports with customizable filters
|
||
- Reduce manager allocation time from 2+ hours to <30 minutes per month
|
||
- Enforce role-based access control (4 personas)
|
||
- Maintain >70% test coverage with comprehensive E2E tests
|
||
|
||
**Non-Goals:**
|
||
- Real-time notifications (deferred to Phase 2, polling is acceptable for MVP)
|
||
- PDF/CSV report exports (deferred to Phase 2, on-screen only for MVP)
|
||
- Time-tracking tool integration (manual entry only for MVP)
|
||
- Multi-tenancy (single-tenant MVP, add tenant_id later)
|
||
- Mobile app (desktop web only)
|
||
- AI-powered forecasting (rule-based validation sufficient)
|
||
|
||
---
|
||
|
||
## Decisions
|
||
|
||
### Decision 1: Two-Container Architecture (Laravel API + SvelteKit Frontend)
|
||
|
||
**Choice:** Separate Laravel API backend and SvelteKit frontend in different containers.
|
||
|
||
**Rationale:**
|
||
- Clean separation of concerns (API vs UI)
|
||
- Easier to scale independently in future
|
||
- SvelteKit is modern and great for dashboards, worth learning curve
|
||
- Laravel provides robust API development (owner has PHP background)
|
||
|
||
**Alternatives Considered:**
|
||
- Laravel + Blade templates: Rejected (less interactive UI, harder for dashboards)
|
||
- Laravel + Vue (Inertia): Rejected (owner preferred Svelte over Vue)
|
||
- SvelteKit full-stack: Rejected (owner has PHP background, prefer Laravel for API)
|
||
|
||
**Implementation:**
|
||
- Frontend: SvelteKit (port 5173), Tailwind CSS + DaisyUI, Recharts, TanStack Table
|
||
- Backend: Laravel 12 (latest) (port 3000), PostgreSQL (latest), Redis (latest)
|
||
- Communication: REST API with Laravel API Resources for consistent JSON
|
||
- Reverse proxy: Existing Nginx Proxy Manager routes `/api/*` → Laravel, `/*` → SvelteKit
|
||
|
||
---
|
||
|
||
### Decision 2: PostgreSQL from Day 1
|
||
|
||
**Choice:** Use PostgreSQL in production and development (no SQLite).
|
||
|
||
**Rationale:**
|
||
- Avoid migration pain later (SQLite → PostgreSQL is error-prone)
|
||
- Production-grade features (JSON operators, full-text search, advanced indexing)
|
||
- Better for reporting queries (complex aggregations, window functions)
|
||
- Docker volume mount preserves portability
|
||
|
||
**Alternatives Considered:**
|
||
- SQLite for local dev, PostgreSQL for prod: Rejected (migration pain, feature parity issues)
|
||
|
||
**Implementation:**
|
||
- PostgreSQL (latest, Alpine container)
|
||
- Volume-mounted to `./data/postgres` for backup/portability
|
||
- Migrations from day 1 (Laravel migrations)
|
||
- UUIDs for primary keys (prevents ID enumeration, easier distributed systems later)
|
||
|
||
---
|
||
|
||
### Decision 3: Redis Caching from Day 1
|
||
|
||
**Choice:** Implement query and response caching with Redis from the start.
|
||
|
||
**Rationale:**
|
||
- Owner insisted: "No need to sweat on refactoring it everywhere"
|
||
- Prevents technical debt accumulation
|
||
- Expensive queries (capacity calculations, reports) benefit immediately
|
||
- Easy automatic cache invalidation with Laravel
|
||
|
||
**Alternatives Considered:**
|
||
- Defer caching to Phase 2: Rejected (owner's preference for avoiding future refactoring)
|
||
|
||
**Implementation:**
|
||
- Redis (latest, Alpine container)
|
||
- Cache keys pattern: `allocations:month:{YYYY-MM}`, `reports:forecast:{from}:{to}:{hash}`
|
||
- TTL: 1 hour (allocations), 15 min (reports), 24 hours (master data)
|
||
- Automatic invalidation on mutations (create/update/delete triggers cache flush)
|
||
- Laravel cache facade for consistency
|
||
|
||
---
|
||
|
||
### Decision 4: JWT Authentication (Token-Based)
|
||
|
||
**Choice:** JWT tokens instead of session-based authentication.
|
||
|
||
**Rationale:**
|
||
- Stateless (better for API-first architecture)
|
||
- Suitable for SPA frontend
|
||
- Easier to add mobile app later (future-proofing)
|
||
- Industry standard for REST APIs
|
||
|
||
**Alternatives Considered:**
|
||
- Laravel sessions: Rejected (owner preferred JWT for future mobile support)
|
||
|
||
**Implementation:**
|
||
- tymon/jwt-auth package
|
||
- Access token: 60 minute TTL
|
||
- Refresh token: 7 day TTL (stored in Redis, one-time use with rotation)
|
||
- Token claims: user UUID, role, permissions array
|
||
- Refresh endpoint rotates tokens on each use
|
||
|
||
---
|
||
|
||
### Decision 5: SvelteKit Frontend Stack
|
||
|
||
**Choice:** SvelteKit + Tailwind CSS + DaisyUI + Recharts + TanStack Table + Superforms + Zod
|
||
|
||
**Rationale:**
|
||
- **DaisyUI**: Fast development, opinionated but speeds up dashboard creation
|
||
- **Recharts**: Good balance of power and simplicity for charts
|
||
- **TanStack Table**: Industry standard for data grids, powerful filtering/sorting
|
||
- **Superforms + Zod**: Type-safe validation, seamless SvelteKit Form Actions integration
|
||
|
||
**Alternatives Considered:**
|
||
- Shadcn/ui: Rejected (DaisyUI faster for MVP)
|
||
- Chart.js: Rejected (Recharts more powerful)
|
||
- Custom table component: Rejected (TanStack is proven, owner unfamiliar but trusts recommendation)
|
||
|
||
**Implementation:**
|
||
- Svelte stores for minimal UI state only (filters, modals)
|
||
- Fetch API for HTTP (no Axios, native is sufficient)
|
||
- Vitest for unit tests, Playwright for E2E tests
|
||
|
||
---
|
||
|
||
### Decision 6: Allocation Validation Strategy
|
||
|
||
**Choice:** Soft validation with visual indicators (GREEN/YELLOW/RED), not hard blocks.
|
||
|
||
**Rationale:**
|
||
- Managers sometimes need flexibility to over-allocate temporarily
|
||
- Hard blocks would frustrate workflow
|
||
- Visual warnings catch errors while allowing override
|
||
- "This money is my salary!" — both over and under-allocation must be flagged
|
||
|
||
**Validation Rules:**
|
||
- GREEN: Allocation = Approved estimate (100%, within ±5% tolerance)
|
||
- YELLOW: Under-allocation (<95% of approved estimate) — will undercharge
|
||
- RED: Over-allocation (>105% of approved estimate) — will overcharge
|
||
- Person capacity: YELLOW warning at >100%, RED alert at >120%
|
||
|
||
**Implementation:**
|
||
- API returns validation status with each allocation response
|
||
- Frontend displays color-coded indicators in allocation matrix
|
||
- Tooltip shows exact variance ("Over by 20 hours, will overcharge client")
|
||
|
||
---
|
||
|
||
### Decision 7: Monthly Aggregate Actuals (Not Daily)
|
||
|
||
**Choice:** Track actual hours as monthly totals, allowing incremental weekly updates.
|
||
|
||
**Rationale:**
|
||
- Monthly planning cycle doesn't require daily granularity
|
||
- Simplifies data model and UI
|
||
- Team members can update weekly and system accumulates
|
||
- No time-tracking integration for MVP (manual entry)
|
||
|
||
**Alternatives Considered:**
|
||
- Daily time logging: Rejected (over-engineering for MVP, adds complexity)
|
||
- Weekly buckets: Rejected (monthly is sufficient given monthly planning cycle)
|
||
|
||
**Implementation:**
|
||
- Actuals table: project_id, team_member_id, month (YYYY-MM), hours_logged
|
||
- UI allows replacing or incrementing monthly total
|
||
- Utilization calculated as: (Actual hours / Capacity) × 100%
|
||
|
||
---
|
||
|
||
### Decision 8: Defer Real-Time Notifications to Phase 2
|
||
|
||
**Choice:** No WebSocket notifications in MVP, users refresh to see changes.
|
||
|
||
**Rationale:**
|
||
- Allocations are planned monthly, not time-critical
|
||
- WebSocket setup adds 6 hours of dev time
|
||
- Polling every 30s is acceptable alternative but also deferred
|
||
- Focus MVP on core allocation/reporting functionality
|
||
|
||
**Alternatives Considered:**
|
||
- WebSocket + 1 notification PoC (6 hours): Rejected (not critical for monthly planning)
|
||
- Polling-based notifications (2 hours): Rejected (also deferred, users can refresh)
|
||
|
||
**Implementation (Phase 2):**
|
||
- Laravel Broadcasting with Redis adapter
|
||
- SvelteKit WebSocket client
|
||
- Events: AllocationCreated, AllocationUpdated, EstimateApproved
|
||
|
||
---
|
||
|
||
### Decision 9: Database Schema Design
|
||
|
||
**Choice:** Normalized schema with master data tables, JSON for forecasted effort, UUIDs for primary keys.
|
||
|
||
**Key Tables:**
|
||
- `team_members`: id (UUID), name, role_id (FK), hourly_rate, active
|
||
- `projects`: id (UUID), code (unique), title, status_id (FK), type_id (FK), approved_estimate, forecasted_effort (JSON)
|
||
- `allocations`: id (UUID), project_id (FK), team_member_id (FK), month (YYYY-MM), allocated_hours
|
||
- `actuals`: id (UUID), project_id (FK), team_member_id (FK), month (YYYY-MM), hours_logged
|
||
- `roles`, `project_statuses`, `project_types`: Master data tables
|
||
- `holidays`, `ptos`: Calendar data
|
||
|
||
**Design Rationale:**
|
||
- **UUIDs**: Prevent ID enumeration attacks, easier distributed systems later
|
||
- **Normalized master data**: Roles/statuses/types in separate tables for dynamic configuration
|
||
- **Month as string (YYYY-MM)**: Simplifies queries, index-friendly, human-readable
|
||
- **JSON for forecasted effort**: Flexible structure `{"2026-02": 40, "2026-03": 60}`, easy to extend
|
||
- **Soft deletes for projects**: `deleted_at` timestamp for audit trail
|
||
- **Active flag for team members**: Preserve historical allocations when person leaves
|
||
|
||
**Indexes:**
|
||
- `allocations`: composite index on (project_id, month), (team_member_id, month)
|
||
- `actuals`: composite index on (project_id, month), (team_member_id, month)
|
||
- `team_members`: index on (role_id, active)
|
||
- `projects`: index on (status_id, type_id), unique on (code)
|
||
|
||
---
|
||
|
||
### Decision 10: API Design Pattern
|
||
|
||
**Choice:** REST API with Laravel API Resources for consistent JSON responses.
|
||
|
||
**Rationale:**
|
||
- REST is simpler than GraphQL for this use case
|
||
- Laravel API Resources provide consistent transformation layer
|
||
- Standard HTTP verbs (GET, POST, PUT, DELETE)
|
||
- Easy to document with Laravel Scribe (SwaggerUI)
|
||
|
||
**Endpoint Structure:**
|
||
```
|
||
/api/auth/login (POST)
|
||
/api/auth/logout (POST)
|
||
/api/auth/refresh (POST)
|
||
|
||
/api/team-members (GET, POST)
|
||
/api/team-members/:id (GET, PUT, DELETE)
|
||
|
||
/api/projects (GET, POST)
|
||
/api/projects/:id (GET, PUT, DELETE)
|
||
|
||
/api/allocations?month=YYYY-MM (GET, POST)
|
||
/api/allocations/bulk (POST)
|
||
/api/allocations/:id (PUT, DELETE)
|
||
|
||
/api/actuals?month=YYYY-MM (GET, POST)
|
||
/api/actuals/bulk (POST)
|
||
/api/actuals/:id (PUT)
|
||
|
||
/api/reports/forecast?from=YYYY-MM&to=YYYY-MM (GET)
|
||
/api/reports/utilization?month=YYYY-MM (GET)
|
||
/api/reports/cost?month=YYYY-MM (GET)
|
||
/api/reports/allocation?month=YYYY-MM (GET)
|
||
/api/reports/variance?month=YYYY-MM (GET)
|
||
|
||
/api/master-data/roles (GET)
|
||
/api/master-data/statuses (GET)
|
||
/api/master-data/types (GET)
|
||
```
|
||
|
||
**Response Format (Laravel API Resources):**
|
||
```json
|
||
{
|
||
"data": { /* resource */ },
|
||
"meta": { /* pagination, counts */ },
|
||
"links": { /* HATEOAS links */ }
|
||
}
|
||
```
|
||
|
||
**Error Format:**
|
||
```json
|
||
{
|
||
"message": "Validation failed",
|
||
"errors": {
|
||
"allocated_hours": ["Must be greater than 0"]
|
||
}
|
||
}
|
||
```
|
||
|
||
---
|
||
|
||
### Decision 11: Testing Strategy
|
||
|
||
**Choice:** >70% code coverage with unit + E2E + regression tests on every change.
|
||
|
||
**Test Layers:**
|
||
- **Backend Unit (PHPUnit)**: Model methods, service classes, utilities
|
||
- **Backend Feature (Pest)**: API endpoints, authentication, authorization
|
||
- **Frontend Unit (Vitest)**: Svelte components, stores, utilities
|
||
- **E2E (Playwright)**: Critical user flows (login → allocate → view reports)
|
||
|
||
**Coverage Targets:**
|
||
- Backend: >80% (easier to test server-side logic)
|
||
- Frontend: >70% (UI testing is harder)
|
||
- Overall: >70% (enforced in `/opsx-verify`)
|
||
|
||
**Test Data Strategy:**
|
||
- Database seeders for test data (Laravel seeders)
|
||
- Factories for model generation (Laravel factories)
|
||
- Test fixtures for E2E tests (Playwright fixtures)
|
||
|
||
**Regression Test Approach (MVP):**
|
||
- Run full test suite on every change
|
||
- E2E tests cover happy paths + critical error cases
|
||
- Phase 2: Issue-driven loop (E2E failure → create GitHub issue → fix → retest)
|
||
|
||
**Implementation:**
|
||
- Pre-commit hooks: Run linters + unit tests
|
||
- CI/CD: Run full suite (unit + E2E) before merge
|
||
- `openspec verify` command: Check coverage, run tests, lint
|
||
|
||
---
|
||
|
||
## Risks / Trade-offs
|
||
|
||
### Risk: SvelteKit Learning Curve
|
||
**Impact:** Owner and associate unfamiliar with Svelte, may slow initial development.
|
||
|
||
**Mitigation:**
|
||
- SvelteKit has excellent documentation
|
||
- Simpler than React/Vue (less boilerplate)
|
||
- TanStack Table is framework-agnostic (owner unfamiliar but AI will guide)
|
||
- Start with simple components, iterate
|
||
|
||
---
|
||
|
||
### Risk: Two-Container Complexity
|
||
**Impact:** More moving parts than single monolith, deployment overhead.
|
||
|
||
**Mitigation:**
|
||
- Docker Compose handles orchestration
|
||
- Code-mounted volumes for hot reload (no rebuild needed)
|
||
- Owner comfortable with Docker
|
||
- Cleaner architecture worth the overhead
|
||
|
||
---
|
||
|
||
### Risk: Over-Allocation Soft Validation
|
||
**Impact:** Managers could ignore RED flags and over-allocate anyway.
|
||
|
||
**Mitigation:**
|
||
- Visual warnings are prominent (RED color, tooltip with exact impact)
|
||
- Reports show over-allocation clearly
|
||
- Phase 2: Add email notifications when allocations exceed threshold
|
||
- Manager discipline assumed (this is their job)
|
||
|
||
---
|
||
|
||
### Risk: Manual Time Entry Accuracy
|
||
**Impact:** Team members may forget to log hours or log inaccurately.
|
||
|
||
**Mitigation:**
|
||
- Utilization reports highlight under-logging (planned > actual consistently)
|
||
- Manager can follow up with team members showing low actuals
|
||
- Phase 2: Integrate with time-tracking tools (Jira, Harvest, Toggl)
|
||
- Incremental weekly updates reduce forgetting
|
||
|
||
---
|
||
|
||
### Risk: Cache Invalidation Bugs
|
||
**Impact:** Stale data shown if cache invalidation logic fails.
|
||
|
||
**Mitigation:**
|
||
- Comprehensive test coverage for cache invalidation logic
|
||
- Redis TTL ensures eventual consistency (max 1 hour stale)
|
||
- Cache keys are scoped (project, month, person)
|
||
- Invalidation triggered on all mutations (create/update/delete)
|
||
- Manual cache flush available for admins
|
||
|
||
---
|
||
|
||
### Risk: JWT Token Security
|
||
**Impact:** Stolen tokens could allow unauthorized access.
|
||
|
||
**Mitigation:**
|
||
- Refresh token rotation (one-time use)
|
||
- Short access token TTL (60 minutes)
|
||
- Refresh tokens stored in Redis (revocable)
|
||
- HTTPS enforced via Nginx Proxy Manager
|
||
- Logout invalidates refresh token
|
||
- Token includes user role for authorization checks
|
||
|
||
---
|
||
|
||
### Trade-off: No Real-Time Notifications
|
||
**Benefit:** Saves 6 hours of dev time, keeps MVP scope tight.
|
||
|
||
**Cost:** Users must manually refresh to see allocation changes.
|
||
|
||
**Justification:** Allocations are monthly planning activity, not time-critical. Acceptable for MVP.
|
||
|
||
---
|
||
|
||
### Trade-off: No PDF/CSV Exports
|
||
**Benefit:** Faster MVP, avoids report formatting complexity.
|
||
|
||
**Cost:** Users cannot export reports for offline viewing or stakeholder sharing.
|
||
|
||
**Justification:** On-screen reports are primary value, exports are nice-to-have for Phase 2.
|
||
|
||
---
|
||
|
||
### Trade-off: Manual Time Entry
|
||
**Benefit:** Avoids vendor lock-in, no integration complexity.
|
||
|
||
**Cost:** Team members must manually enter hours monthly.
|
||
|
||
**Justification:** Monthly aggregate is low overhead (~5 minutes per person per month).
|
||
|
||
---
|
||
|
||
## Migration Plan
|
||
|
||
**Deployment Steps:**
|
||
|
||
1. **Initial Setup:**
|
||
- Run `docker-compose up` (creates 4 containers)
|
||
- Laravel migrations create database schema
|
||
- Database seeders populate master data (roles, statuses, types)
|
||
- Create superuser account via Laravel seeder
|
||
|
||
2. **Data Import (Optional):**
|
||
- If team has historical spreadsheet data, create import script
|
||
- Import team members (name, role, hourly rate)
|
||
- Import active projects (code, title, approved estimate)
|
||
- Do NOT import historical allocations (start fresh)
|
||
|
||
3. **User Onboarding:**
|
||
- Train managers on allocation workflow (1 hour session)
|
||
- Demo: capacity planning → project setup → allocation → reports
|
||
- Provide Quick Start guide (Markdown doc)
|
||
|
||
4. **Go-Live:**
|
||
- Managers create February 2026 capacity plan (holidays, PTO, availability)
|
||
- Managers allocate resources for February
|
||
- Team members log February actuals mid-month (incremental updates)
|
||
- Month-end: Review utilization reports, adjust March allocations
|
||
|
||
**Rollback Strategy:**
|
||
- MVP is greenfield (no data migration to revert)
|
||
- If critical bug discovered, roll back to previous container image
|
||
- Docker Compose down/up with previous image tag
|
||
- PostgreSQL data persisted in volume (safe across container restarts)
|
||
- Zero-downtime rollback: Blue/green deployment (Phase 2, not needed for MVP)
|
||
|
||
**Monitoring (Phase 2):**
|
||
- Application logs (Laravel log files)
|
||
- Database performance (PostgreSQL slow query log)
|
||
- Cache hit rate (Redis INFO stats)
|
||
- API response times (Laravel Telescope or custom middleware)
|
||
|
||
---
|
||
|
||
## Open Questions
|
||
|
||
### Question 1: Hourly Rate Visibility
|
||
Should developers see their own hourly rate, or only managers/top brass?
|
||
|
||
**Options:**
|
||
- A) Developers can see their own rate (transparency)
|
||
- B) Developers cannot see rates (only allocations)
|
||
|
||
**Recommendation:** A (transparency fosters trust, rate is not secret in most orgs)
|
||
|
||
**Decision:** To be finalized with owner before implementation.
|
||
|
||
---
|
||
|
||
### Question 2: Hours Per Day Configuration
|
||
Is "1.0 availability = 8 hours" globally configured, or per-project?
|
||
|
||
**Options:**
|
||
- A) Global setting (e.g., 1.0 = 8 hours for everyone)
|
||
- B) Per-team member (some people work 6-hour days)
|
||
- C) Per-project (different billing rates for different project types)
|
||
|
||
**Recommendation:** A (global setting, simplest for MVP)
|
||
|
||
**Decision:** Owner mentioned "configurable per project" but likely meant per team. Clarify.
|
||
|
||
---
|
||
|
||
### Question 3: PTO Approval Workflow
|
||
Is PTO auto-approved, or does it require manager approval?
|
||
|
||
**Options:**
|
||
- A) Auto-approved (capacity reduced immediately)
|
||
- B) Requires approval (pending state until manager approves)
|
||
|
||
**Recommendation:** B (manager approval, prevents abuse)
|
||
|
||
**Decision:** Owner likely expects approval workflow. Confirm.
|
||
|
||
---
|
||
|
||
### Question 4: Support Projects in Revenue Forecast
|
||
Should "Support" type projects appear in revenue forecasts?
|
||
|
||
**Options:**
|
||
- A) Exclude from revenue (they're ongoing ops, not billable)
|
||
- B) Include in revenue (still billable internally)
|
||
|
||
**Recommendation:** Ask owner's preference (may vary by org)
|
||
|
||
**Decision:** To be confirmed during implementation.
|
||
|
||
---
|
||
|
||
### Question 5: Allocation Tolerance Threshold
|
||
What's the tolerance for "within estimate" (GREEN indicator)?
|
||
|
||
**Current assumption:** ±5% (e.g., 100-hour project allocated 95-105 hours is GREEN)
|
||
|
||
**Confirm:** Is 5% the right threshold, or should it be configurable?
|
||
|
||
**Decision:** Start with 5%, make configurable in Phase 2 if needed.
|
||
|
||
---
|
||
|
||
**End of Design Document**
|
||
|
||
**Next Steps:**
|
||
1. Review open questions with owner
|
||
2. Finalize database schema (ERD diagram)
|
||
3. Create tasks.md (implementation checklist)
|
||
4. Begin Sprint 1: Docker Compose setup + database migrations
|