ADDED Requirements

Requirement: Generate multi-period forecast report

The system SHALL generate forecast reports showing allocations and revenue projections across multiple months.

Scenario: View 3-month forecast

  • WHEN a manager requests a forecast report for February-April 2026
  • THEN the system displays all projects with allocations in that period
  • AND for each project shows month-by-month allocation breakdown
  • AND calculates revenue forecast based on allocations × hourly rates

Scenario: Forecast includes variance indicators

  • WHEN viewing the forecast report
  • THEN the system shows forecasted hours vs approved estimate for each project
  • AND displays GREEN/YELLOW/RED indicators for over/under-allocation

Requirement: Filter forecast by project

The system SHALL allow filtering forecast reports by project, status, or type.

Scenario: Filter by project status

  • WHEN filtering forecast report to show only "In-Progress" projects
  • THEN the system displays only projects with that status

Scenario: Filter by project type

  • WHEN filtering forecast report to show only "Project" type (billable)
  • THEN the system excludes "Support" type projects from the report

Requirement: Filter forecast by team

The system SHALL allow filtering forecast reports by team or team member.

Scenario: Filter by team member

  • WHEN filtering forecast report to show allocations for "John Doe"
  • THEN the system displays only projects where John Doe has allocations

Scenario: Filter by role/team

  • WHEN filtering forecast report to show allocations for "Backend Developer" role
  • THEN the system displays allocations for all team members with that role

Requirement: Forecast revenue calculation

The system SHALL calculate revenue forecasts based on allocations multiplied by team member hourly rates.

Scenario: Calculate monthly revenue forecast

  • WHEN a project has allocations: Developer A 40h @ $150/h, Developer B 30h @ $125/h
  • THEN the system calculates monthly revenue forecast as $9,750 (40×$150 + 30×$125)

Scenario: Calculate total revenue forecast for period

  • WHEN viewing forecast for Feb-Apr
  • AND total allocations are: Feb $9,750, Mar $12,000, Apr $6,000
  • THEN the system calculates total period revenue forecast as $27,750

Requirement: Forecast summary aggregations

The system SHALL provide summary aggregations across all projects in the forecast.

Scenario: Total approved hours vs allocated hours

  • WHEN viewing forecast summary
  • THEN the system displays total approved estimate across all projects
  • AND displays total allocated hours across all projects
  • AND shows overall variance percentage

Scenario: Revenue forecast summary

  • WHEN viewing forecast summary
  • THEN the system displays total possible revenue (if all projects delivered at 100% allocation)
  • AND displays current forecasted revenue based on actual allocations

Requirement: Customizable date range

The system SHALL allow selecting custom date ranges for forecast reports.

Scenario: Select date range

  • WHEN a manager selects "From: 2026-02" and "To: 2026-06"
  • THEN the system generates forecast for those 5 months